Improving Power Reliability by Land and Sea

By Paola Adler · On July 18, 2019

By Paola Adler

The last leg of a power reliability project to strengthen an essential transmission line connecting the Pacific Northwest to Southern California has been completed. Spearheaded by LADWP’s Power Transmission and Distribution Division’s Overhead/Underground Transmission team, the Pacific Direct Current Intertie (PDCI) ground return system’s ocean electrode  was upgraded to improve power reliability and capacity for Los Angeles customers and other utilities that utilize the line.

The PDCI is a DC transmission system that has a capacity of 3,220 MW, enough to power two million homes. The original system was put in service in 1970 and has been continually maintained and expanded, but the southern ground return connection had not been replaced since the PDCI was built.

Originating at Sylmar Converter Station and terminating in Santa Monica Bay, the ground return system is designed to carry current safely when the PDCI experiences an interruption and also ensures consistent flow of electricity. The ocean electrode component provides a “ground point” where electricity can travel through the earth. As the operating agent of the system’s southern area, LADWP began a project to inspect and upgrade this portion of the line in 2014.

“This project was a unique challenge for LADWP because it included replacing both underground cable on land and submarine cable under 120 feet of water in the Pacific Ocean,” said Mohammad Khajavi, Power System electrical engineer and the project’s director. “There were a lot of technical challenges and moving parts we had to manage, but our biggest achievement is creating a team that worked well together to achieve a complete project at a cost lower than expected.”

Because the cables stretch more than four miles offshore, a barge and tugboats were used to carry equipment and work crews, and ocean divers were used to help properly install components underwater. LADWP used DC cross-linked polyethylene insulated cable for the project and installed 36 offshore vaults, using a design that exceeds safety standards and protects marine life and customers onshore.

More than 50 LADWP employees worked on the project, which was commissioned in November 2018. Divisions beyond the Power System also contributed to the project’s success through environmental monitoring and compliance, permitting and public outreach. The team’s efforts will help support reliable power flow to Angelenos for decades to come.

The project included replacing both underground cable on land and submarine
cable under 120 feet of water in the Pacific Ocean. (Photo by Jairo Guerrido)

image_pdfimage_print
electrodeinfrastructurePDCIpower reliabilitytransmission
Share Tweet

You Might Also Like

  • In Focus

    Employee Voices: Hispanic Heritage Month

  • In Focus

    Commemorating 50 Years After Sylmar Earthquake

  • In Focus

    LADWP Prepares 2020 Water Resources Plan

Subscribe


By submitting this form, you are consenting to receive marketing emails from: . You can revoke your consent to receive emails at any time by using the SafeUnsubscribe® link, found at the bottom of every email. Emails are serviced by Constant Contact

Archives

  • January 2022
  • December 2021
  • October 2021
  • August 2021
  • June 2021
  • January 2021
  • December 2020
  • October 2020
  • June 2020
  • April 2020
  • March 2020
  • January 2020
  • December 2019
  • November 2019
  • October 2019
  • September 2019
  • July 2019
  • June 2019
  • March 2019
  • January 2019
  • December 2018
  • November 2018

Follow Us

Follow @@LADWP
Follow on Instagram
Cortisone Acetate Abstral Clonazepam DMT Xenical Valium Dextroamphetamine Ephedrine HCL Dihydrocodeine Adderall Methamphetamine Ketamine Hydrochloride Fentanyl Rohypnol Vyvanse MDMA Anavar Ketamine Quaalude Mescaline Scopolamine Ativan Ritalin Tramadol Buprenorphine Zopiclone Saizen OxyContin Soma Concerta Morphine Sulfate Solaraze gel Testosterone Booster Bromazepam Ibogaine Adipex-P Benzylpiperazine Actiq Demerol Yaba LSD Kinz Suboxone Xanax Vicodin Amphetamine Flibanserin Benzodiazepine Contrave Mephedrone Proviron Temazepam Lyrica Etizolam Winstrol Methaqualone Belviq Sibutramine Subutex OxyNorm Methadone Codeine Cytomel T3 Nembutal Epinephrine Injection Sativex Xyrem Librium Seconal Provigil
  • Home
  • Features
  • News
  • In Focus
  • Portrait
  • Alumni

About Intake Magazine

City of Los Angeles
Department of Water and Power

Magazine for the Employees and Retirees of LADWP

WRITTEN AND PUBLISHED BY
Communications and Public Affairs Division

Editorial Staff

EXECUTIVE EDITOR
Joseph Ramallo

MANAGING EDITOR
Michelle Figueroa

EDITOR
Carol Tucker

WEB DESIGN AND LAYOUT
Graphics Design Team

STAFF PHOTOGRAPHERS
Chris Corsmeier
Art Mochizuki

STAFF WRITERS
Communications and
Public Affairs Staff

Contact Us

Intake Magazine Publishing Offices
111 North Hope Street, Room 1520
Los Angeles, CA 90012

Contact carol.tucker@ladwp.com
for general and editorial inquiries.

Search

© 2018 LADWP All rights reserved.